MC-21 airliner faces one-year delay due to U.S. sanctions
The Russian airliner schedule will reportedly be delayed until 2021 as U.S. sanctions have interrupted the supply of composite materials for the aircraft.
Russia’s MC-21 airliner schedule will reportedly be delayed until 2021 according to .
During a Feb. 18 news conference at the International Defense Exhibition (IDEX), Sergey Chemezov, CEO of Russian state-owned holding conglomerate Rostec (Moscow, Russia) — who has launched an audit of the program after assuming ownership of the program from United Aircraft Corp. (UAC, Moscow, Russia) — reportedly claimed the delay was triggered by U.S. sanctions on production facilities and suppliers.
The sanctions are said to have prevented Hexcel (Stamford, Conn., U.S.) and Toray (Tokyo, Japan) from supplying composite materials for the aircraft and will likely cause disruption at the aircraft’s final assembly site in Irkutsk, Siberia. According to Chemezov, Rostec has commissioned Rosatom (Moscow, Russia) to develop and qualify replacement composite materials. He also stated that although delivery of PW1400G engines for the first batch of MC-21s is still expected from Pratt & Witney (East Hartford, Conn., U.S.), Rostec subsidiary United Engine Corp. is also working on its PD-14 turbofan as an alternative engine.
Related Content
-
Welding is not bonding
Discussion of the issues in our understanding of thermoplastic composite welded structures and certification of the latest materials and welding technologies for future airframes.
-
Combining multifunctional thermoplastic composites, additive manufacturing for next-gen airframe structures
The DOMMINIO project combines AFP with 3D printed gyroid cores, embedded SHM sensors and smart materials for induction-driven disassembly of parts at end of life.
-
Plant tour: Aernnova Composites, Toledo and Illescas, Spain
RTM and ATL/AFP high-rate production sites feature this composites and engineering leader’s continued push for excellence and innovation for future airframes.